{"id":2336,"date":"2013-12-04T13:26:59","date_gmt":"2013-12-04T13:26:59","guid":{"rendered":"http:\/\/manajemenproyekindonesia.com\/?p=2336"},"modified":"2020-11-14T16:01:59","modified_gmt":"2020-11-14T16:01:59","slug":"responsibility-for-the-commissioning-process-in-epc-projects","status":"publish","type":"post","link":"https:\/\/manajemenproyekindonesia.com\/?p=2336","title":{"rendered":"Responsibility for the Commissioning Process in EPC Projects"},"content":{"rendered":"<p style=\"text-align: justify;\"><a href=\"http:\/\/manajemenproyekindonesia.com\/wp-content\/uploads\/2013\/12\/strategic-commissioning.jpg\"><img decoding=\"async\" loading=\"lazy\" class=\"alignleft size-thumbnail wp-image-2337\" title=\"strategic-commissioning\" src=\"http:\/\/manajemenproyekindonesia.com\/wp-content\/uploads\/2013\/12\/strategic-commissioning-150x150.jpg\" alt=\"\" width=\"150\" height=\"150\" srcset=\"https:\/\/manajemenproyekindonesia.com\/wp-content\/uploads\/2013\/12\/strategic-commissioning-150x150.jpg 150w, https:\/\/manajemenproyekindonesia.com\/wp-content\/uploads\/2013\/12\/strategic-commissioning.jpg 300w\" sizes=\"(max-width: 150px) 100vw, 150px\" \/><\/a>The commissioning process &#8211; involving start-up, commissioning and performance  testing &#8211; is critical to the success of an engineering, procurement and    construction (EPC) project. Responsibility for this phase of the project must    be properly allocated between the parties and a balance needs to be struck between    the competing interests of the various stakeholders; this requires a sound understanding    of the pertinent issues, some of which are considered in this update.<!--more--><\/p>\n<p style=\"text-align: justify;\">&nbsp;<\/p>\n<p style=\"text-align: justify;\">The nature of the facility may make it more logical for one party  rather than    another to take responsibility for the commissioning process. If the  facility    consists of multiple plants which are to interface with each other,  but each of which is to be constructed by a different EPC contractor, no  individual contractor    will wish to bear the risk of other contractors&#8217; failures at the  interface points.    The owner may therefore be in the best position to run coordinated and  properly    interfaced commissioning process. Conversely, if a single contractor  is responsible    for the delivery of the entire facility, there may be little practical  advantage    in having the owner coordinate and control the commissioning process.<\/p>\n<p style=\"text-align: justify;\">If the contractor is responsible for the commissioning process, the handover of    the facility to the owner will not take place until the performance tests have    been completed, and the owner will be unable to operate the facility commercially    until after the handover. If the owner is responsible for the commissioning process, it will    have control of the facility and will therefore be able to begin commercial operation    earlier. However, the extent of the benefits arising from early operation may    depend on the intended off take arrangements. In addition, the owner should ensure    the contract is drafted in such a way that early commercial operation does not    enable the contractor to argue that the owner has accepted the facility as complete,    which could result in the owner losing the benefit of the performance guarantees    and so having little recourse against the contractor if a performance failure    is subsequently detected.<\/p>\n<p style=\"text-align: justify;\">In circumstances where the owner is responsible for the commissioning  process, the care,    custody and control of the facility will have been transferred from  the contractor    to the owner before the start of the commissioning process. The  contractor will not want to be exposed to delay-liquidated damages after  such handover. Consequently, the owner will have little if any recourse  against the contractor for delays which occur    during the commissioning process, regardless of whether such delays  result from defects in    the facility which are attributable to the contractor. The question  then arises    as to how the owner will cover additional costs arising from such  delays. This    may prompt funders to require additional completion support in order  to cover    the owner&#8217;s exposure to delay risk.<\/p>\n<p style=\"text-align: justify;\">If the owner is responsible for the commissioning process, it is more likely that acts or    omissions of the owner or its personnel during the commissioning process will have an impact on the performance    of the facility, making it easy for the contractor to argue    that a performance failure has been caused by the owner and is not attributable    to the contractor, or that the owner has failed to follow the performance-testing    procedures set out in the contract. In <em>Yorkshire Water Services Ltd v Taylor    Woodrow Construction Northern Ltd<\/em> [2004] EWHC 1660 an owner was unable to    recover damages from a contractor in relation to certain costs, defects and    performance failures due to the manner in which the owner had undertaken the    commissioning and testing of a wastewater treatment facility. A properly drafted    contract can help to avoid such a situation, even if the owner or its personnel    are involved in the commissioning process (eg, if the owner&#8217;s personnel are    seconded to the contractor and assist the contractor under its direction and    control). However, if the contractor retains responsibility for the commissioning    process, this goes a long way towards ensuring that the performance    guarantees remain valid, thereby reducing funder completion support requirements.<\/p>\n<p style=\"text-align: justify;\">Allocation of responsibility for the commissioning process will almost inevitably    require a balancing of the contract price against the funder completion support    requirements. The owner may seek to minimize completion support requirements    by requiring the contractor to take responsibility for the commissioning process.    If it does so, it must accept that the contract price will be higher due to the    cost and risk to the contractor associated with such responsibility. Alternatively,    the owner may seek to reduce the contract price and accept additional funder    completion support requirements by taking responsibility for the commissioning    process itself. In assessing this issue, the owner must consider that, although    completion support may have a more direct impact on sponsors, it is at least    contingent: it will be paid only if the relevant risks arise. An increased contract price is payable in any case.<\/p>\n<p style=\"text-align: justify;\">No single factor is likely to determine which party should take  responsibility    for the commissioning process under an EPC contract. The decision  should    be based on an analysis of the technical constraints, legal pitfalls  and the requirements    of the lending market, as well as accepted industry practice. The  contract must properly document the allocation of responsibility based  on a clear    understanding of this analysis. The complexity and interdependence of  the issues    involved dictate that financial, technical and legal advisers play a    role in the allocation of responsibility for the process. Although of  vital    importance to the success of a project, the completion of the process  may not    be the end of matters. Detailed defect rectification regimes    and ongoing warranties may regulate the rights of the parties to the  contract    long after the process has been completed.<\/p>\n<p style=\"text-align: justify;\">&nbsp;<\/p>\n<p style=\"text-align: justify;\"><em>Reference by Andrew Chapman<\/em><\/p>\n<p style=\"text-align: justify;\"><em><br>\n<\/em><\/p>\n\n\n<p><sub><em>Untuk melihat daftar artikel \u21d2\u00a0<strong><a href=\"http:\/\/manajemenproyekindonesia.com\/?page_id=44\">Table of Content<\/a><\/strong><\/em>, <em>dan konsultasi Project Management \u21d2\u00a0<strong><a href=\"http:\/\/manajemenproyekindonesia.com\/?page_id=3054\">Konsultasi<\/a><\/strong>.<\/em> <em>Daftar karya ada pada \u21d2\u00a0<strong><a href=\"https:\/\/manajemenproyekindonesia.com\/?page_id=4873\">Innovation Gallery<\/a><\/strong><\/em>, <em>dan daftar riset pada \u21d2\u00a0<a href=\"https:\/\/manajemenproyekindonesia.com\/?page_id=4904\"><strong>Research Gallery<\/strong><\/a><\/em><\/sub><\/p>\n","protected":false},"excerpt":{"rendered":"<p>The commissioning process &#8211; involving start-up, commissioning and performance testing &#8211; is critical to the success of an engineering, procurement and construction (EPC) project. Responsibility for this phase of the project must be properly allocated between the parties and a balance needs to be struck between the competing interests of the various stakeholders; this requires [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_s2mail":"yes","spay_email":""},"categories":[189,12],"tags":[505,3512,206,3511,857,3515,236,71,504,3513],"jetpack_featured_media_url":"","_links":{"self":[{"href":"https:\/\/manajemenproyekindonesia.com\/index.php?rest_route=\/wp\/v2\/posts\/2336"}],"collection":[{"href":"https:\/\/manajemenproyekindonesia.com\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/manajemenproyekindonesia.com\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/manajemenproyekindonesia.com\/index.php?rest_route=\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/manajemenproyekindonesia.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=2336"}],"version-history":[{"count":2,"href":"https:\/\/manajemenproyekindonesia.com\/index.php?rest_route=\/wp\/v2\/posts\/2336\/revisions"}],"predecessor-version":[{"id":6783,"href":"https:\/\/manajemenproyekindonesia.com\/index.php?rest_route=\/wp\/v2\/posts\/2336\/revisions\/6783"}],"wp:attachment":[{"href":"https:\/\/manajemenproyekindonesia.com\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=2336"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/manajemenproyekindonesia.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=2336"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/manajemenproyekindonesia.com\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=2336"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}